Construction Update

By June 14, 2018Construction

Neo is now move-in ready!

 

FEBRUARY 2019

// Final walkthroughs and move-ins completed with final community touches completed.

 

JANUARY 2019

// First and second-floor owners begin their preoccupancy walkthroughs early January. Final finishing work and deficiencies completed before move-ins.

 

DECEMBER 2018

// Interior and exterior finishing ongoing with landscaping being completed by end of the month. Third and fourth-floor owners begin their preoccupancy walkthroughs mid-December.

 

NOVEMBER 2018

// Asphalt is down and lines are painted, retaining wall behind the building is complete and remaining landscaping work has begun.

4th floor finish painting completed with countertops and cabinetry installed. 3rd floor will complete finish painting early November with countertops and cabinetry installed. 2nd-floor cabinets are installed, countertops will be done early November with finish painting to follow. 1st-floor flooring has been completed, cabinets will be installed early November and countertops are coming later in November.

 

OCTOBER 2018

// Solar panels have been installed, rooftop patio post and beams have been completed with glass railings going in late October.

4th floor suite interiors have floors, cabinets, and casing/baseboards completed. Finish painting to be completed the week of October 22nd. Other floor interiors also in progress.

Exterior sidewalks, curbs, asphalt prep is underway and set for paving late October.

 

SEPTEMBER 2018

// Drywall nearing completion with mudding and taping underway on upper floors. Painting to begin later this month.

 

AUGUST 2018

// Insulation and drywall continue as well as electrical, sprinklers, heating, and A/C rough-ins.

 

JULY 2018

// Drywall and insulation began on the fourth and third floor.

 

JUNE 2018

// Roofing will be complete by end of June with windows and door install nearing completion. Fireboarding and vinyl decking is also underway.

 

MAY 2018

// Poured suspended slab early May. As of May 16th, second-floor framing has been completed and third-floor framing has begun. Plumbing and electrical rough-ins are scheduled to start at the end of the month.

 

APRIL 2018

// Completed the ground works and prepping for the slab on grade for the parkade. Shoring for the suspended slab and backfilling was completed as well as the prefabbing of walls completed off-site.

 

MARCH 2018

// Footings were poured early March and the foundation wall formwork was started. Walls and columns were recently completed as the team headed into the Easter long weekend.

Book A Viewing

To book an appointment and view our condo quality rental suites, please fill out the form below.

VIP Registration

Join our VIP Registration list to receive NEO updates and suite selection priority.